OAC provided cost control and owner's representative services when construction was approximately 40% complete and the owner
was facing nearly $10 million in changes and additions to the contract.
OAC implemented a strict regimen of cost accountability and procedures for tracking and negotiating costs. The project was completed within 15 days of the original schedule while saving nearly $1.5 million. |
Location: Renton, Washington Project Cost: $40 million Project Area: 320,000 square feet |